Home

Controlling-Excellence — OEE Estimation

Estimation of OEE (Overall Equipment Effectivness) based on 24 hours

Avaliability Performance Quality
Not scheduled Unscheduled Actual speed Max speed Quality Losses

Losses

Planned shut down

hours
Breakdown
Setup & Adjustment
hours
Reduced speed
Small Stops
Output/hour
Max. (Target) speed

Output/hour
Startup Rejects
Production rejects
Pieces
Planned Production
Time
in hours
Operating
Time
in hours
Total Output
Actual
in pieces
Theoretical
Output
in pieces
Good Output

in pieces
h h pcs pcs pcs

Operating Time /
Planned Prod. Time

Total Output /
Theoretical Output

Good Output /
Total Output
% % %

The six big losses

Avaliability

Breakdown: equipment failure, tooling failure, unplanned maintenance
Setup and Adjustment: changeover, material shortage, warm-up time

Performance

Reduced Speed: rough running, equipment wear, operator inefficiency, incorrect settings
Small Stops: obstructed flow, jam, missfeed, sensor blocked, cleaning, checking

Quality

Startup Rejects: scrap, rework, in process damage, incorrect assembly
Production Reject: same as startup but during production

Impressum:
Ralf Platvoet
Diplom Ökonom
Beratender Volks- und Betriebswirt
Hentzenallee 24 - 42897 Remscheid - Deutschland
Fon:+49 17695602269 - Fax:+49 (0) 2191 5655 422 - Email : info(at)platvoet.org
Webseite: www.platvoet.org
Umsatzsteuer-Identifikationsnummer gemäß § 27 a Umsatzsteuergesetz: DE 208322644
Inhaltlich Verantwortlicher gemäß § 55 Abs. 2 RStV: Ralf Platvoet
Die Berechnungen dienen der Demonstration der Rechenwege und liefern gerundete Werte.
Für die weitere Verwendung der berechneten Ergebnisse wird keine Haftung übernommen.